Cost and schedule overruns in large hydropower dams: an assessment of projects completed since 2000

Publication date

2020

Authors

Plummer Braeckman, Judith
Disselhoff, Tim
Kirchherr, J.W.ISNI 0000000464978446

Editors

Advisors

Supervisors

Document Type

Article

Collections

Open Access logo

License

cc_by

Abstract

This paper presents novel data on cost and schedule overruns in recent dam projects started and completed since 2000 and compares them with pre-existing data sets on projects started before 2000. Combining these data, a meta-data set was created of 184 cost overrun and 191 time overrun data points. For post-2000 projects, the average cost overrun was 33% and schedule overrun was 18% as compared with 46% and 37% respectively for pre-2000 projects. While a decrease in the averages was observed, the change in cost overruns is not statistically significant, whereas the change in time overruns is significant.

Keywords

Large dams, hydorpower, forecasting, cost and schedule estimates, World Commission on Dams, Taverne, SDG 7 - Affordable and Clean Energy

Citation

Plummer Braeckman, J, Disselhoff, T & Kirchherr, J W 2020, 'Cost and schedule overruns in large hydropower dams: an assessment of projects completed since 2000', International Journal of Water Resources Development, vol. 36, no. 5, pp. 839-854. https://doi.org/10.1080/07900627.2019.1568232